Fugro has completed offshore works undertaken in preparation for full construction of the European Offshore Wind Deployment Centre (EOWDC) at Aberdeen Bay, Scotland

The geotechnical site investigation took place at 11 turbine locations to assess the seabed, with the data acquired being used to inform the final design and micro-siting of the turbine foundations. Full offshore construction is scheduled to start in late 2017 or early 2018, after an investment decision later this year.
Fugro’s dynamically-positioned 78-metre geotechnical drilling vessel, the Bucentaur, was mobilised to the EOWDC site, located about 2km to 5km off the coast of Aberdeen. The site investigation work was on behalf of Aberdeen Offshore Wind Farm Limited (AOWFL). …. 